Friday, June 24, 2005

LEED Credit 5 – Measurement and Verification - Part I

Lesson Learned: Make sure that you have proper metering for the 10 required loads for LEED. If you do not provide the proper metering you will need to comply with Option D of the 2001 International Performance Measurement & Verification Protocol (IPMVP) Volume I: Concepts and Options for Determining Energy and Water Savings. Which requires you to calibrate the energy simulation and model; calibrated with hourly or monthly utility billing data and/or end-use metering.

-Lighting systems and controls
-Constant and variable motor loads
-Variable frequency drive (VFD) operation
-Chiller efficiency at variable loads (kW/ton)
-Cooling load
-Air and water economizer and heat recovery cycles
-Air distribution static pressures and ventilation air volumes
-Boiler efficiencies
-Building-related process energy systems and equipment
-Indoor water risers and outdoor irrigation systems

Make sure that the Engineer provides meters for each of these loads!!

Thursday, June 23, 2005

USGBC Developing LEED® for Homes Certification

WASHINGTON-The Home Depot Foundation is giving the U.S. Green Building Council (USGBC) a $375,000 grant to help develop the LEED™ for Homes (LEED-H) Rating System. Pilot projects to test LEED-H certification requirements are scheduled for this summer in several states.



Wednesday, June 22, 2005

LEED IAQ Testing - Part 1

Per the LEED-NC EQ3.2 credit, in lieu of conducting a two-week building flush-out with new MERV 13 filtration media at 100% outside air, one can conduct a baseline indoor air quiality testing procedure consistent with the US EPA's current "Protocol for Enviromental Requirements, Baseline IAQ and Materials, for the Research Triangle Park Campus, Section 01445.

Now the LEED-CI EQ3.2 credit has a less intensive testing protocol than the original EPA Research Triangle Park (RTP) post-construction IEQ testing procedure

Post Construction-Pre-Occupancy Indoor Air Test Scope of Work

Test Requirements
Conduct a baseline indoor air quality testing procedure that randomly selects sampling points for every 25,000 square feet, or for each contiguous floor area, whichever is larger, to measure the maximum concentration levels for the chemical contaminates listed below:

Chemical Contaminant Maximum Concentration Reference Standard
- Carbon Monoxide: (CO) 9 parts per million and no greater than 2 parts per million above outdoor levels
- Carbon Dioxide (CO2) 530 parts per million* ASHRAE 62-1999
- Formaldehyde 50 parts per billion (State of Washington IAQ Standard)
- Particulates 150 micrograms per cubic meter (EPA National Ambient Air Quality Standard)
- TVOC 500 micrograms per cubic meter (State of Washington IAQ Standard)
- 4-PCH 6.5 micrograms per cubic meter (State of Washington IAQ Standard)

(* This measurement is required only if the building is regularly occupied during the testing. Measured differential between indoor and outdoor conditions is based on occupancy type as defined by ASHRAE 62-1999. Maximum concentration differential in parts per million = 10,300 / ventilation rate in cubic feet per minute.)


Performance
The tests shall be conducted before the arrival of furniture and occupants and after all construction activities are completed, including punch list items, and final touch up painting/sanding/finishing in order to not have those activities negatively effect the testing and sample collection.

For each building area where the maximum concentration limits for any one test are exceeded, stop sample collection, notify the owner, and recommend actions to mitigate cause. Then retest the indoor air quality levels to indicate the requirements are achieved.

Submittals
Provide a copy of the IAQ testing results indicating the methods used and measured chemical contaminate concentrations compared to the maximum chemical contaminate concentration requirements noted above. Reported concentration units of measure should be consistent with those stated in the maximum limits noted above.

Monday, June 13, 2005

Which LEED credits are related to Commissioning?

Energy and Atmosphere is the only category that directly requires commissioning. However, the requirements of credit 3 of Water Efficiency and all credits of Environmental Quality will more easily be met if a commissioning process is in place.

Energy and Atmosphere-17 points

Prerequisite 1 – Fundamental Building Systems Commissioning: Requires the hiring of a commissioning agent, documenting design intent, including Cx in DDs, utilize a Cx Plan, verify installation, FT, training and documentation, final Cx report.

Prerequisite 2 – Minimum Energy Performance: Building is designed to the more stringent of the local energy code or ASHRAE/IESNA 90.1-1999 – verification part of Cx Authority's design review service.

Prerequisite 3 – CFC Reduction in HVAC&R Equipment: Zero use of CRC refrigerants in new buildings/phasing out program in existing buildings. Cx Authority in particular can advise of alternatives that will meet this and credit 4 - Elimination of HCFC’s and Halons.

Credit 1 – Optimize Energy Performance: Receive points based on % of design energy cost saved by implementing Energy Conservation Measures as compared to the energy cost budget for energy components described in ASHRAE/IESNA 90.1-1999. % determined by building simulation using Energy Cost Budget Method. With the Cx Authority's lessons learned/design experience, we can review the design for possible energy savings measures not already in the documents.

Credit 2 – Renewable Energy: Receive points for using alternative energy sources, such as wind energy, biomass, geothermal, high temp solar, biogas. This is fairly dependent on project location, in some instances project generated power can be sold back to the local power grid.

Credit 3 – Additional Commissioning: Receive points for Cx design review (DD and CD), review of select submittals, re-commissioning management manual, post occupancy/end of warranty review (seasonal testing, review of operation and outstanding issues).

Credit 4 - Elimination of HCFC’s and Halons: Requires HVAC and fire suppression equipment that does not use HCFC refrigerants or Halons. Cx Authority can advise of alternatives.

Credit 5 – Measurement and Verification: Requires continuous monitoring of lighting systems and controls, motor loads, VFD operation, Chiller efficiencies (KW/ton), cooling load, economizers, heat recovery, system static pressures, OA volumes, boiler efficiencies, building specific process energy systems, indoor water risers and outdoor irrigation systems. The commissioning process will verify the accuracy, operation and reporting of the metering required to meet this credit. The Cx Authority can produce the Measurement and Verification Plan.

Credit 6 – Green Power: Requires using power generated from renewable sources for a two year period.

Water Efficiency-5 points

Credit 3 – Water Use Reduction: Requires reducing the consumption of potable water by % less than the baseline calculated for the building after meeting the Energy Policy Act of 1992. While this is a design issue, Cx will assist with compliance through the submittal process.

Indoor Environmental Quality-15 points

Prerequisite 1 – Minimum IAQ Performance: meet ASHRAE 62-1999. The Cx Authority will review compliance as part of the design intent documentation review and project drawing review.

Prerequisite 2 – Environmental Tobacco Smoke (ETS) Control: Requires zero exposure of nonsmokers to tobacco smoke by prohibiting smoking in the building or by providing designated smoking areas with proper ventilation. If smoking areas are designated in the building, the Cx process will verify capture of smoke and operation of ventilation equipment.

Credit 1 – Carbon Dioxide Monitoring: Requires monitoring of building CO2 levels throughout the building. The Cx process will verify calibration and initial setpoints of the sensors and verify equipment reactions to high levels.

Credit 2 – Increased Ventilation Effectiveness: Requires mechanically ventilated buildings to have air change effectiveness rating greater than or equal to 0.9 (requires specialized tracer gas testing), or a design narrative that describes compliance with ASHRAE Fundamentals Chapter 31 – Space Air Diffusion (points are easier to achieve if the design implements this from the get go). The Cx process can assist in either of these methods. We can administer the tracer gas testing or review the design for compliance with Chapter 31.

Credit 3 – Construction IAQ Management Plan: Points obtained for meeting minimum requirements of SMACNA IAQ guidelines and protect on-site absorptive materials from moisture and replace filtration media before occupancy. Points obtained for conducting a two-week building flush with new filtration and 100% OA after construction and before occupancy or performing baseline IAQ testing per EPA protocol. Both of these points can be obtained with a properly executed IAQ plan. The Cx process can assist in producing or reviewing the plan, and documenting implementation.

Credit 4 – Low-Emitting Materials: Requires the reduction in use of odiferous adhesives, sealants, paints, composite wood products and carpets. The Cx process can document the compliance for this credit by obtaining the MSDS and cut sheets for material used from the appropriate contractors.

Credit 5 – Indoor Chemical and Pollutant Source Control: Requires the design to avoid exposure of occupants to potentially hazardous chemicals, such as housekeeping areas, copy/print rooms, provide appropriate plumbing for chemical waste, and implement systems that will capture particulate/dirt at high traffic entries/exits. The Cx process can review these issues during DD and CD review periods.

Credit 6 – Controllability of Systems: Requires one operable window and one lighting control zone per 200 sqft for all occupied areas within 15 feet of the perimeter wall for one point. Requires individual control for airflow, temperature, lighting for 50% of the non-perimeter, regularly occupied areas. Again, a design issue that can be verified by the Cx Authority during DD and CD review. Actual operation of the controls will be verified during functional testing.

Credit 7 – Thermal Comfort: Compliance with ASHRAE 55-1992, Addenda 1995, for temperature and humidity control. An additional point is obtained by installing a temperature and humidity monitoring system that gives operators control. The Cx process will document compliance with ASHRAE during design intent and will verify calibration and operation of any temperature and humidity monitoring system during functional testing.

Credit 8 – Daylight and Views: Requires a minimum Daylight Factor of 2% in 75% of all spaces occupied for critical visual tasks. Requires a direct line of sight to vision glazing from 90% of all regularly occupied spaces. The Cx process can evaluate compliance during the design review process.

Friday, June 10, 2005

GREENGUARD Certification Program™

The GREENGUARD Certification Program™ is an independent, third-party testing program for low-emitting products and materials. Access to the GREENGUARD Product Guide, an indoor air quality (IAQ) resource, is provided at no charge. The guide features products, which are regularly tested to ensure that their chemical and particle emissions meet acceptable IAQ pollutant guidelines and standards. GREENGUARD Certification is a valuable tool for architects, designers, product specifiers, and purchasing organizations that want to locate, specify, and purchase off-the-shelf, low-emitting products for indoor environments. GREENGUARD Certification is a voluntary program available to all manufacturers and their suppliers.

http://www.greenguard.org

Thursday, June 09, 2005

EPA/OPPT - Green Buildings

EPA/OPPT - Green Buildings

Monday, June 06, 2005

Environmental Valuation & Cost-Benefit News - U.S. General Service Administration Green Building Cost Study

Environmental Valuation & Cost-Benefit News - U.S. General Service Administration Green Building Cost Study

Manipulated Media: USGBC to provide guidelines for equipment and refrigerant selection

Manipulated Media: USGBC to provide guidelines for equipment and refrigerant selection